Make Up Your Mind Mother Nature: Construction Law and Weather Delays

My children have been mad at Mother Nature over the past month.  One day ... jeans, turtle necks and jackets.  The next day ... shorts and flip-flops.  At least in the South we have not had to deal with 30 inches of snow like on the East Coast.  That kind of weather can cripple a construction project and cause months of delay to the schedule.

Weather Delays on Construction Project

As Spring approaches, how do you address the impact of unusually severe weather?  Traditionally, the parties' construction contract will dictate who bears the risk of loss in these types of situations.  Here are some general rules:

  • The contractor is usually entitled to additional contract time, but not additional compensation for weather delays.  The AIA contract documents provide that "if adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction."  The ConsensusDOCs provide that "if the Contractor is delayed at any time in the commencement or progress of the Work by any cause beyond the control of the Contractor, the Contractor shall be entitled to an equitable extension of the Contract Time. Examples of causes beyond the control of the Contractor include, but are not limited to, the following: ... adverse weather conditions not reasonably anticipated ..."
  • Delays must be attributable to "unusually severe" weather or weather "not reasonably anticipated."  Of course, by its very nature, such a claim will be factually driven. The contractor should be prepared to establish this by reasonable documentation, such as weather data from the National Oceanic and Atmospheric Administration.
  • Weather analysis should be geographically limited.  Having moved from Washington, D.C. to Nashville in 2006, I can appreciate this point.  The entire Middle Tennessee closes down, including the government and schools, at the slightest hint of snow (...exaggerated slightly ...), but it takes 30 inches in D.C. to paralyze the roads and commuters.  The point is that "unusually severe weather" on a Nashville construction site may be different than a site in the nation's capitol.
  • The delays must actually impact the schedule.  While you may think that down-time due to weather should automatically entitle the contractor to a time extension, it will depend largely on the contract provision addressing weather delays. You will have to determine whether the inclement weather affected material delivery, access to the site, safety measures, etc.

As with most other issues involving time and money, the parties' contract will determine what happens when Mother Nature refuses to cooperate with your construction schedule.

Lessons from a Bankruptcy Judge: Learn How to Write

"Pay me less before the dispute erupts ... or pay me more after the dispute erupts ..." is a phrase that many construction litigators have said to their clients.  What that means, practically, is that if you invest the time and money to have your attorney review construction contracts before the job starts, you will save time, money and effort later when the dispute begins (and perhaps you may even fend it off). Despite the warnings, there are many out there who want to "go it alone" ... and that's okay.  This post is for you.

Learn to Write Better

The American Bar Journal posted an article two weeks ago about a federal bankruptcy judge who was fed up with "superfluous words and too much capitalization."   The judge took a stand against legalese and issued some guidelines (pdf) to the practicing bankruptcy attorney.  Some of my favorites include:

  • Lawyers apparently disfavor articles, both definite and indefinite. Use the
    articles “the,” “a,” and “an” as appropriate.
    Write the way you would speak.
  • Never use and/or.
  • Eliminate superfluous words. They serve no purpose other than to make the
    document sound more legal ... Examples of such words are: “hereby,” “herein,”
    “in and for,” “subject,” “that certain,” “now,” “that,” “undersigned,”
    “immediately,” “heretofore entered in this case,” “be, and hereby is”–the list
    goes on and on.
  • Keep plurals and possessives straight and consistent. Know when to use
    debtors (plural), debtor’s (singular possessive), and debtors’ (plural
    possessive). Make sure the verb matches the subject of the sentence.

You can tell by the terse language in the judge's guidelines that he likes clarity and he wants litigants (and particularly their attorneys) to follow those guidelines.  If I were a construction litigator ... which I am ... I wonder what my suggested guidelines would be for construction contracts.  Here are a few:

  • Keep the names consistent.  I know this will take some searching and replacing in your form contracts, but it is important to track the parties' names correctly.  Many times, I have found a "subcontractor" listed as "contractor" in one section and "subcontractor" in another section.
  • Identify the "contract documents" for the parties.  Too many disputes arise because someone thinks the proposal or purchase order is part of the parties' agreement only to learn later that it has not been incorporated as part of the contract documents.  Many form contracts have an "order of precedence" clause that ranks the precedential value of the documents in the event of a dispute.  Make sure to expressly include every document that you want into the contract documents.
  • Evaluate and clarify the "dispute" provisions.  Again, I have seen a number of lawsuits between parties spend too much time on the procedural issues such as litigation, arbitration, mediation (because the contract was not clearly written), rather than getting to the heart of the matter.  Make sure your contracts clearly identify your method of dispute resolution.

Do you have any other guidelines for your construction contracts?

Photo: Flckr - LucasTheExperience

Hot Off the Press: ConsensusDOCS Releases Green Building Addendum

As much as possible, I like to highlight various forms of construction contract documentsIn most of my green building presentations over the past few months, I have talked about the "soon to be released" Green Building Addendum from ConsensusDOCS.  Well, that day has finally come!

New ConsensusDOCS Green Building Addendum

Based upon my preliminary review of the 310 Green Building Addendum, I am confident to say that the blogosphere of architects, engineers, owners, contractors, LEED AP-ers, and attorneys is going to be jumping.  There are a lot of new terms, such as Elected Physical Green Measures and Elected Green Status; there is a new contractual party, called the Green Building Facilitator (or "GBF"); and there is a meaty "Risk Allocation" section in the document. 

The first seven sections of the 310 Green Building Addendum include the following:

  1. General Principles, including an acknowledgment that Green Measures are being incorporated into the project that affect the roles and responsibilities of the parties.
  2. Definitions, which introduce and define all the new players, roles and responsibilities.
  3. Green Requirements and Procedures, which are elected by the owner.
  4. Green Building Facilitator, which addresses who this person will be and what his role will be.
  5. Green Status, which sets the targeted status (i.e., LEED Certified Silver).
  6. Green Measures, which outlines the steps to achieve the Green Status.
  7. Plans and Specifications, which helps incorporate the green measures into the underlying contract documents.

Section 8 addresses risk allocation, which is where I will probably spend a couple of days digesting.  In this section, you will find issues such as:

  • The role of the contractor during the process, as well as a provision that limits the contractor's responsibility for performing certain services. 
  • A waiver of consequential damages, which is the provision that every green attorney will want to take a look at first.
  • A general limitation of liability provision that addresses the failure to attain the targeted status, as well as, the failure to receive any intended benefits to the environment.

One cursory review ... and I did not find anything absolutely surprising.  I was interested to see that the contract document was not LEED-driven, meaning that the drafters wrote the green measure provisions and the green status provisions broad enough to include all existing and any future green building programs.

ConsensusDOCS Beats AIA to the Punch: Releases Federal Gov't Contract

In case you have not heard, on June 11, 2009, ConsensusDOCS released what is reported to be the first and only standard contract designed specifically for federal government construction projects. The ConsensusDOCS 752-Subcontract for Federal Construction Projects provides all of the necessary terms and conditions essential to comply with the Federal Acquisition Regulation ("FAR"). In addition to being FAR compliant, the ConsensusDOCS 752 includes all of the federally-mandated flow-down provisions. The release is important in light of the federal stimulus funding bill. McGraw-Hill Construction has a good summary of the new contract document here.

According to Tom Kelleher, Senior Partner in Smith, Currie & Hancock LLP and Chair of the national coalition of associations who wrote and endorse the new standard contract, the new "federal subcontract will keep needed construction projects from getting tangled up in red tape.”

Of course, the American Institute of Architects was not totally out of the race. The now discontinued and retired AIA A-201 SC 1999 included the Federal Supplementary Conditions for public construction projects that could be incorporated into the contract documents.

 
[an error occurred while processing this directive] [an error occurred while processing this directive]