Make Up Your Mind Mother Nature: Construction Law and Weather Delays

My children have been mad at Mother Nature over the past month.  One day ... jeans, turtle necks and jackets.  The next day ... shorts and flip-flops.  At least in the South we have not had to deal with 30 inches of snow like on the East Coast.  That kind of weather can cripple a construction project and cause months of delay to the schedule.

Weather Delays on Construction Project

As Spring approaches, how do you address the impact of unusually severe weather?  Traditionally, the parties' construction contract will dictate who bears the risk of loss in these types of situations.  Here are some general rules:

  • The contractor is usually entitled to additional contract time, but not additional compensation for weather delays.  The AIA contract documents provide that "if adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction."  The ConsensusDOCs provide that "if the Contractor is delayed at any time in the commencement or progress of the Work by any cause beyond the control of the Contractor, the Contractor shall be entitled to an equitable extension of the Contract Time. Examples of causes beyond the control of the Contractor include, but are not limited to, the following: ... adverse weather conditions not reasonably anticipated ..."
  • Delays must be attributable to "unusually severe" weather or weather "not reasonably anticipated."  Of course, by its very nature, such a claim will be factually driven. The contractor should be prepared to establish this by reasonable documentation, such as weather data from the National Oceanic and Atmospheric Administration.
  • Weather analysis should be geographically limited.  Having moved from Washington, D.C. to Nashville in 2006, I can appreciate this point.  The entire Middle Tennessee closes down, including the government and schools, at the slightest hint of snow (...exaggerated slightly ...), but it takes 30 inches in D.C. to paralyze the roads and commuters.  The point is that "unusually severe weather" on a Nashville construction site may be different than a site in the nation's capitol.
  • The delays must actually impact the schedule.  While you may think that down-time due to weather should automatically entitle the contractor to a time extension, it will depend largely on the contract provision addressing weather delays. You will have to determine whether the inclement weather affected material delivery, access to the site, safety measures, etc.

As with most other issues involving time and money, the parties' contract will determine what happens when Mother Nature refuses to cooperate with your construction schedule.

State Football Playoffs: Excusable Delay on Construction Project?

College football in the Midwest.  No further comment needed.  So it should come as no surprise to see that a construction project in Mishawaka, Indiana was "postponed" as the local football team advanced to the state playoffs.

Football Excusable Delay?

Although the school's request to hold off the work crews affected construction for only a few days—and there was no indication that the postponement significantly delayed the completion of the work—it does raise some questions about excusable delays.  

Generally, the parties' contract will determine whether a delay is excusable or non-excusable. Some typical examples of excusable delay include:

  • Design problems
  • Differing site conditions
  • Changes in the work
  • Force majeure (i.e., Acts of God, unusually severe weather, riots, war, labor disputes)  

In some instances, the contract will contain an exhaustive list of those events or circumstances where a delay to the contractor's work will be excused.  In other instances, the contract may simply define an excusable delay as "any delay to the work that is beyond the contractor's control and without the fault or negligence of the contractor.

On the other hand, non-excusable delays are traditionally the responsibility of the contractor. Examples of non-excusable delay may include:

  • Non-conforming or defective work
  • Failure to adequately plan or schedule the work
  • Inadequate manpower
  • Any other delay within the contractor's control

In these instances, the contractor is generally not entitled to a time extension, is not entitled to additional compensation for the extra time on the project or work performed, and may even be responsible for liquidated damages.

When there is a delay to the work, what should you do?  Although you may have different options depending on whether you are the owner, contractor or supplier ... or depending on whether the project is public or private ... here are some tips:

  1. Review the delay provisions of the agreement.  Because these provisions vary from contract to contract, it is critical to understand what will be considered excusable.  The real issue here is to determine what will be the litmus test in determine whether the non-performance or delay in the work should be excused for some reason beyond the performing party's control.  
  2. Determine whether a time extension is warranted.  As you review the delay provisions, the next step is to determine what relief will be given if the delay is determined to be excusable.  For example, the contract may allow for a contract time extension, additional compensation, and relief from liquidated damages when the delay is found to be excusable or beyond the performing party's control.
  3. Consider whether the delay is concurrent.  Many times the contractor's work may be delayed by more that one cause—one that is excusable and one that is non-excusable.  In this instance, depending on the applicable law, the court may either: (a) deny any recovery whatsoever because the delays were caused, in part, by the contractor; or (b) apportion the delay damages between the responsible parties.

For some additional thoughts on delay claims, see Tim Hughes' articles (part 1, part 2) on his former law firm website. 

Construction Management Tip: Fix Problem Now, Point Finger Later

Finger Point Later?When my kids break something in the house, they immediately begin pointing the finger at the "alleged" responsible actor.  In the construction world, many times you will need to fix the problem first and then point the finger later. 

I read an article today by Jack Broom in the Seattle Times that illustrates this point.  The incident involved two massive tunneling machines that were damaged and awaiting costly repairs ... 300 feet below ground!  The 17.5 foot diameter machines are supposed to be boring a 13-mile tunnel to take waste water to Puget Sound.  Rather than the five-feet-per-hour pace that these machines should be boring through compacted wet dirt, they are dead stopped awaiting repairs.  According to the article, more than 120 workers have been laid off until the machines are fixed and each day of delay adds to the owner's more than $1.8 billion in escalating costs.  It may take another month or two before the machines can be fixed and start boring again.

This story represents what should be happening on the construction project gone wild scenario: 

For now, [according to the owner's project manager], the county, the contractor and the machines' manufacturer are working together on "getting the fix in place and getting these tunnel-boring machines moving again ... It's in everybody's interest to complete this job as quickly as possible."

Although the parties are reportedly working to find a common solution to repair the two machines so that the contractor can complete the work, legal responsibility for the delays will need to be determined.  Including the legal questions highlighted in Broom's article, a court may be asked to resolve the following:

  • Were there any subsurface reports performed prior to the start of the work?
  • Did the owner have any contractual responsibility for subsurface conditions?
  • Did the contractor have any contractual responsibility for its own inspection of subsurface conditions?
  • Did the owner/architect have any ongoing supervisory or inspection duties during performance of the work?
  • Were the machines properly mobilized and operated during construction?
  • Were the machines defective in any way?
  • Were there any other concurrent delays affecting the work?

For owners/developers, this incident is an example of how unexpected events on a construction project require a multi-phased approach to the problem.  Your situation may dictate that you quickly assess the extent of the damage, determine a workable and cost effective solution and fix the problem first ... and leave leave the finger-pointing to later.  So long as you reserve your rights in accordance with the notice provisions of your contract, the project completion will be better served in this approach.

Contractors should take heed that when your work is delayed for reasons beyond your reasonable control, there may be contractual and legal defenses to an owner's assessment of liquidated damages.  Of course, the immediate goal will be to get the project back on schedule ... but remember the finger may be pointed at you sometime down the road.

 
[an error occurred while processing this directive] [an error occurred while processing this directive]