Spearin and Luria Bros: Two Cases Every Federal Contractor Should Know

Where is the best place to start when you have been away from work for a family emergency? Naturally, you go back to the basics.  In my next few posts, I review some of the "basic building block" or "essential" construction cases every contractor should know.  The first two are Spearin and Luria Bros.

U.S. v. Spearin, 248 U.S. 132 (1918) is perhaps the most important construction case to understand.  Spearin established the well-known rule that the government/owner impliedly warrants the adequacy of its design. The United States Supreme Court held that detailed specifications describing the work "imported a warranty that if the specifications were followed, the sewer would be adequate. This implied warranty is not overcome by general disclaimer clauses requiring the contractor to examine the site, check the plans and specifications and assume responsibility for the work until completed." The rule, which has come to be known as the Spearin Doctrine, has, for years, allowed contractors to recover the costs incurred as a result of defective design specifications provided by the government. The Spearin Doctrine has been adopted by most states.

In Luria Bros. v. U.S., 369 F.2d 701 (Ct. Cl. 1966), the Court of Claims further expanded upon the Spearin Doctrine to make clear that the government must timely correct its defective design. The court found that the original specifications were defective.  When defective specifications delay the work, the court reasoned, the contractor is entitled to recover damages. In Luria Bros., the government was dilatory in recognizing the need for and in revising defective specifications, which constituted a breach of the implied obligation not to do anything that would hinder or delay the contractor’s performance.

Both Spearin and Luria Bros. provide a legal assurance to contractors that additional costs may be recovered for defects in the design by the owner.

Next post features what is an equitable adjustment.

Image: stevendepolo

The Spearin Doctrine In Less Than 140 Characters

Tweeting Supreme Court DecisionsA fellow Twitter friend, @danielschwartz, promoted a technology symposium on his Connecticut Employment Law Blog yesterday.  In order to spread the word about the symposium, he challenged his readers and fellow Twitter followers to tweet about their favorite Supreme Court case in less than 140 characters.  

As I thought about the construction industry, there was only one decision that kept coming to mind.  It involved a contractor who agreed to build a dry-dock in the Brooklyn Navy Yard.  In order to build the dry-dock in the site selected for it, the contractor was required to relocate a portion of a sewer that ran through the specified site. The owner (the United States) provided the plans and specifications for the sewer that was to be relocated.  The contractor completed the work according to the plans and specifications.  The owner approved and accepted the work.  But wait ... about a year after the relocation of the sewer, a dam in a connecting sewer caused flooding in the area excavated for the dry-dock. This dam was not shown on the owner's plans and specifications.  That's the background and here is my tweet: 

US v. Spearin: Owner designs. Contractor builds. Owner accepts. Work sucks. Owner sues. Contractor absolved. Owner loses.

If you live in the government contracting world, don't start sending me emails about how wrong I have described the Spearin Doctrine above.  Let me expand my statement beyond 140 characters and give you some more information about the 1918 decision in United States v. Spearin:

  • The Rule. The Spearin Doctrine is legal principle that holds that when a contractor follows the plans and specifications furnished by the owner, and those plans and specifications turn out to be defective or insufficient, the contractor is not liable to the owner for any loss or damage resulting from the defective plans and specifications.
  • Exceptions to the Rule.  In 2007, the Ohio Supreme Court rocked the construction law world by significantly limiting the application of the Spearin Doctrine.  In Dugan & Meyers Construction Co. v. Ohio Dept. of Administrative Services, the trial court applied the Spearin rule in favor of the contractor based upon alleged damages from the impact of an excessive amount of design changes.  On appeal, the Ohio Supreme Court reversed, holding that the Spearin Doctrine did not apply to cases involving delays due to design changes. Rather, the court focused its decision on the “no damages for delay” and “written requests for time extension” clauses in the contract.  Specifically, the court concluded: “We observed that the Spearin Doctrine does not invalidate an express contractual provision.” 
  • Applicability to Green Construction.  Last year, fellow blogger Chris Cheatham suggested that there could be a green Spearin Doctrine.  I am confident that the Spearin Doctrine would be applied equally to non-green construction projects and LEED certified projects, As noted by Chris, a guarantee by the contractor could invalidate any Spearin Doctrine defense by the contractor.  Sounds like the Ohio Supreme Court, right?  The Spearin Doctrine cannot invalidate an express contractual provision.

Any Spearin tid-bits that you would like to share? 

 
[an error occurred while processing this directive] [an error occurred while processing this directive]