Many delay, disruption, and loss of productivity claims are lost or substantially reduced in value because mistakes, errors and carelessness are reflected in the original schedule and plan of operations. The original schedule is often the first piece of documentation that the owner receives demonstrating the contractor’s professionalism in planning and management.

Contractors should pay