When dealing with construction claims—whether one for construction defects, outstanding payment, or delay damages—an initial hurdle is making sure that proper notice has been given.  Generally, you have to make sure that you comply with the contract or insurance provisions by: (1) giving written notice of the claim; (2) to the correct party; (3) within

Words matter. Grammar matters. Even punctuation matters:

Let’s eat, Grandma!

Let’s eat Grandma!

For one government contractor, its claim was recently rejected by the Civilian Board of Contract Appeals because the Board found that the Contractor did not properly state its claim.  In Construction Group LLC v. Dept. of Homeland Security, 15-1 BCA para.

In anticipation of what could be an influx of wintry weather, the Tennessee Department of Transportation has made arrangements to ensure the state’s roadways stay clear. According to the Johnson City Press, TDOT has distributed more than 200,000 tons of salt and 2 million gallons of brine to stations in each of the state’s

My mentor and good friend, Cordell Parvin, has over the years shared with me some great best practices for contractors—whether talking about bid protests, accidents on the jobsite, or filing a claim.

money2

Recently, Cordell sent me a list of items that all contractors should review when developing a request for additional compensation.  I have

Earlier this week, a settlement was reached in dispute where the contractor and designer were alleged to have filed false claims with the U.S. Government on two road projects in South Carolina.  The issue raises an important question: What should a contractor do during negotiations to allow for some “bargaining room” so as to avoid

A number of families will be traveling this holiday weekend, and some are travel-savvy enough to check out travel websites like www.911.Virginia.org for real-time traffic information and identification of construction delays.  When savvy contractors face delays on a project, they immediately take steps to provide notice, document, evaluate and plan for recovery from those delays.

Recovery for unreasonable delays caused by others can be based upon a breach of an implied obligation not to hinder or delay the other party’s performance. Wow, that’s a mouthful! Let’s look at an example.

In Foster & Creighton Company v. Wilson Contracting, the Tennessee Court of Appeals reviewed a case involving a project