When Hurricane Helene struck North Carolina, it caused severe disruptions to construction projects across the state. Baxter International’s North Cove facility in Marion, N.C., was completely shut down after floodwaters damaged the site and bridges leading to it. Elsewhere, landslides and floods wiped out large sections of Interstate 40, making transportation of materials and equipment

Yesterday, I posted about potential construction delays and supply chain challenges resulting from the strike at the East Coast ports, such as New York, New Jersey, Savannah, and Charleston.

A reader asked me about the specific types of construction materials that may be subject to delays. Geographically, the East Coast ports handle a variety

At midnight on October 1, 2024, longshoremen and harbor workers at major East Coast ports went on strike, causing significant disruptions to the flow of goods and materials of all sorts, including those essential for the construction industry. The strike has brought operations at ports like New York, New Jersey, Charleston, and Savannah—key entry points

Last month, a construction worker died as a storm swept through a construction site in Lebanon, Indiana. The preliminary investigation determined that the contractor was on an elevated platform while working on an industrial warehouse that was under construction. The man and other workers were in the process of stopping due to approaching thunderstorms.